G.R. No. 180388 January 18, 2011
SO ORDERED. 6
SO ORDERED.8
MARIA LOURDES P. A. SERENO
Associate Justice
WE CONCUR:
Chief Justice
Footnotes
1 Rollo at 10-32.
4 Petitioners’ Answer, rollo at 56-59.
7G.R. Nos. 151373-74, November 17, 2005, 475 SCRA 218.
8 Rollo at 47.
9 G.R. No. 158253, March 2, 2007, 517 SCRA 255.
12 G.R. No. 95938, August 16, 1991, 200 SCRA 705.
13 G.R. 131544, March 16, 2001, 354 SCRA 566.
14 Supra at note 7.
17 G.R. No. 186192, August 25, 2010.
18 G.R. No. 131544, March 16, 2001, 354 SCRA 566.
GREGORIO R. VIGILAR, SECRETARY OF THE
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (DPWH), DPWH UNDERSECRETARIES
TEODORO E. ENCARNACION AND EDMUNDO E. ENCARNACION AND EDMUNDO V. MIR,
DPWH ASSISTANT SECRETARY JOEL L. ALTEA, DPWH REGIONAL DIRECTOR VICENTE
B. LOPEZ, DPWH DISTRICT ENGINEER ANGELITO M. TWAÑO, FELIX A. DESIERTO OF
THE TECHNICAL WORKING GROUP VALIDATION AND AUDITING TEAM, AND LEONARDO
ALVARO, ROMEO N. SUPAN, VICTORINO C. SANTOS OF THE DPWH PAMPANGA 2ND
ENGINEERING DISTRICT, Petitioners,
vs.
ARNULFO D. AQUINO, Respondent.
vs.
ARNULFO D. AQUINO, Respondent.
D E C I S I O N
SERENO, J.:
Before the Court is a Petition for Review on Certiorari1 under Rule 45 of the Rules of Court, assailing the Decision2 of the Court of Appeals in C.A.-G.R. CV No. 82268, dated 25 September 2006.
The antecedent facts are as follows:
On 19 June 1992, petitioner Angelito M. Twaño, then
Officer-in-Charge (OIC)-District Engineer of the Department of Public
Works and Highways (DPWH) 2nd Engineering District of Pampanga sent an
Invitation to Bid to respondent Arnulfo D. Aquino, the owner of A.D.
Aquino Construction and Supplies. The bidding was for the construction
of a dike by bulldozing a part of the Porac River at Barangay
Ascomo-Pulungmasle, Guagua, Pampanga.
Subsequently, on 7 July 1992, the project was awarded
to respondent, and a "Contract of Agreement" was thereafter executed
between him and concerned petitioners for the amount of PhP1,873,790.69,
to cover the project cost.
By 9 July 1992, the project was duly completed by
respondent, who was then issued a Certificate of Project Completion
dated 16 July 1992. The certificate was signed by Romeo M. Yumul, the
Project Engineer; as well as petitioner Romeo N. Supan, Chief of the
Construction Section, and by petitioner Twaño.
Respondent Aquino, however, claimed that
PhP1,262,696.20 was still due him, but petitioners refused to pay the
amount. He thus filed a Complaint3
for the collection of sum of money with damages before the Regional
Trial Court of Guagua, Pampanga. The complaint was docketed as Civil
Case No. 3137.
Petitioners, for their part, set up the defense4
that the Complaint was a suit against the state; that respondent failed
to exhaust administrative remedies; and that the "Contract of
Agreement" covering the project was void for violating Presidential
Decree No. 1445, absent the proper appropriation and the Certificate of
Availability of Funds.5
On 28 November 2003, the lower court ruled in favor of respondent, to wit:
WHEREFORE, premises considered, defendant
Department of Public Works and Highways is hereby ordered to pay the
plaintiff Arnulfo D. Aquino the following:
1. PhP1,873,790.69, Philippine Currency, representing actual amount for the completion of the project done by the plaintiff;
2. PhP50,000.00 as attorney’s fee and
3. Cost of this suit.
It is to be noted that respondent was only asking for
PhP1,262,696.20; the award in paragraph 1 above, however, conforms to
the entire contract amount.
On appeal, the Court of Appeals reversed and set aside the Decision of the lower court and disposed as follows:
WHEREFORE, premises considered, the appeal is
GRANTED. The "CONTRACT AGREEMENT" entered into between the
plaintiff-appellee’s construction company, which he represented, and the
government, through the Department of Public Works and Highway (DPWH) –
Pampanga 2nd Engineering District, is declared null and void ab initio.
The assailed decision of the court a quo is hereby REVERSED AND SET ASIDE.
In line with the pronouncement in Department of Health vs. C.V. Canchela & Associates, Architects,7
the Commission on Audit (COA) is hereby ordered to determine and
ascertain with dispatch, on a quantum meruit basis, the total obligation
due to the plaintiff-appellee for his undertaking in implementing the
subject contract of public works, and to allow payment thereof, subject
to COA Rules and Regulations, upon the completion of the said
determination.
No pronouncement as to costs.SO ORDERED.8
Dissatisfied with the Decision of the Court of
Appeals, petitioners are now before this Court, seeking a reversal of
the appellate court’s Decision and a dismissal of the Complaint in Civil
Case No. G-3137. The Petition raises the following issues:
1. WHETHER OR NOT THE COURT OF APPEALS ERRED IN HOLDING THAT THE DOCTRINE OF NON-SUABILITY OF THE STATE HAS NO APPLICATION IN THIS CASE.2. WHETHER OR NOT THE COURT OF APPEALS ERRED IN NOT DISMISSING THE COMPLAINT FOR FAILURE OF RESPONDENT TO EXHAUST ALL ADMINISTRATIVE REMEDIES.3. WHETHER OR NOT THE COURT OF APPEALS ERRED IN ORDERING THE COA TO ALLOW PAYMENT TO RESPONDENT ON A QUANTUM MERUIT BASIS DESPITE THE LATTER’S FAILURE TO COMPLY WITH THE REQUIREMENTS OF PRESIDENTIAL DECREE NO. 1445.
After a judicious review of the case, the Court finds the Petition to be without merit.
Firstly, petitioners claim that the Complaint filed
by respondent before the Regional Trial Court was done without
exhausting administrative remedies. Petitioners aver that respondent
should have first filed a claim before the Commission on Audit (COA)
before going to the courts. However, it has been established that the
doctrine of exhaustion of administrative remedies and the doctrine of
primary jurisdiction are not ironclad rules. In Republic of the
Philippines v. Lacap,9
this Court enumerated the numerous exceptions to these rules, namely:
(a) where there is estoppel on the part of the party invoking the
doctrine;
(b) where the challenged administrative act is patently
illegal, amounting to lack of jurisdiction;
(c) where there is
unreasonable delay or official inaction that will irretrievably
prejudice the complainant;
(d) where the amount involved is relatively
so small as to make the rule impractical and oppressive;
(e) where the
question involved is purely legal and will ultimately have to be decided
by the courts of justice;
(f) where judicial intervention is urgent;
(g) where the application of the doctrine may cause great and
irreparable damage;
(h) where the controverted acts violate due process;
(i) where the issue of non-exhaustion of administrative remedies has
been rendered moot;
(j) where there is no other plain, speedy and
adequate remedy;
(k) where strong public interest is involved; and
(l)
in quo warranto proceedings.
In the present case, conditions (c) and (e)
are present.
The government project contracted out to respondent
was completed almost two decades ago. To delay the proceedings by
remanding the case to the relevant government office or agency will
definitely prejudice respondent. More importantly, the issues in the
present case involve the validity and the enforceability of the
"Contract of Agreement" entered into by the parties. These are questions
purely of law and clearly beyond the expertise of the Commission on
Audit or the DPWH. In Lacap, this Court said:
... It does not involve an examination of the
probative value of the evidence presented by the parties. There is a
question of law when the doubt or difference arises as to what the law
is on a certain state of facts, and not as to the truth or the falsehood
of alleged facts. Said question at best could be resolved only tentatively by
the administrative authorities. The final decision on the matter rests
not with them but with the courts of justice. Exhaustion of
administrative remedies does not apply, because nothing of an
administrative nature is to be or can be done. The issue does not
require technical knowledge and experience but one that would involve
the interpretation and application of law. (Emphasis supplied.)
Secondly, in ordering the payment of the obligation
due respondent on a quantum meruit basis, the Court of Appeals correctly
relied on Royal Trust Corporation v. COA,10 Eslao v. COA,11 Melchor v. COA,12 EPG Construction Company v. Vigilar,13 and Department of Health v. C.V. Canchela & Associates, Architects.14
All these cases involved government projects undertaken in violation of
the relevant laws, rules and regulations covering public bidding,
budget appropriations, and release of funds for the projects.
Consistently in these cases, this Court has held that the contracts were
void for failing to meet the requirements mandated by law; public
interest and equity, however, dictate that the contractor should be
compensated for services rendered and work done.
Specifically, C.V. Canchela & Associates is
similar to the case at bar, in that the contracts involved in both cases
failed to comply with the relevant provisions of Presidential Decree
No. 1445 and the Revised Administrative Code of 1987. Nevertheless,
"(t)he illegality of the subject Agreements proceeds, it bears emphasis,
from an express declaration or prohibition by law, not from any
intrinsic illegality. As such, the Agreements are not illegal per se, and the party claiming thereunder may recover what had been paid or delivered."15
The government project involved in this case, the
construction of a dike, was completed way back on 9 July 1992. For
almost two decades, the public and the government benefitted from the
work done by respondent. Thus, the Court of Appeals was correct in
applying Eslao to the present case. In Eslao, this Court stated:
...the Court finds that the contractor should be duly
compensated for services rendered, which were for the benefit of the
general public. To deny the payment to the contractor of the two
buildings which are almost fully completed and presently occupied by the
university would be to allow the government to unjustly enrich itself
at the expense of another. Justice and equity demand compensation on the
basis of quantum meruit. (Emphasis supplied.)
Neither can petitioners escape the obligation to
compensate respondent for services rendered and work done by invoking
the state’s immunity from suit. This Court has long established in
Ministerio v. CFI of Cebu,16 and recently reiterated in Heirs of Pidacan v. ATO,17
that the doctrine of governmental immunity from suit cannot serve as an
instrument for perpetrating an injustice to a citizen. As this Court
enunciated in EPG Construction:181avvphi1
To our mind, it would be the apex of injustice and
highly inequitable to defeat respondent’s right to be duly compensated
for actual work performed and services rendered, where both the
government and the public have for years received and accepted benefits
from the project and reaped the fruits of respondent’s honest toil and
labor.
x x x x x x x x x
Under these circumstances, respondent may not validly
invoke the Royal Prerogative of Dishonesty and conveniently hide under
the State's cloak of invincibility against suit, considering that this
principle yields to certain settled exceptions. True enough, the rule, in any case, is not absolute for it does not say that the state may not be sued under any circumstance.
x x x x x x x x x
Although the Amigable and Ministerio cases generously
tackled the issue of the State's immunity from suit vis a vis the
payment of just compensation for expropriated property, this Court
nonetheless finds the doctrine enunciated in the aforementioned cases
applicable to the instant controversy, considering that the ends of
justice would be subverted if we were to uphold, in this particular
instance, the State's immunity from suit.
To be sure, this Court — as the staunch guardian
of the citizens' rights and welfare — cannot sanction an injustice so
patent on its face, and allow itself to be an instrument in the
perpetration thereof. Justice and equity sternly demand that the State's
cloak of invincibility against suit be shred in this particular
instance, and that petitioners-contractors be duly compensated — on the
basis of quantum meruit — for construction done on the public works
housing project. (Emphasis supplied.)
WHEREFORE, in view of the foregoing, the Petition is DENIED for lack of merit. The assailed Decision of the Court of Appeals in CA-G.R. No. 82268 dated 25 September 2006 is AFFIRMED.
SO ORDERED.MARIA LOURDES P. A. SERENO
Associate Justice
WE CONCUR:
RENATO C. CORONA
Chief Justice
Chief Justice
ANTONIO T. CARPIO Associate Justice |
CONCHITA CARPIO MORALES Associate Justice |
PRESBITERO J. VELASCO, JR. Associate Justice |
ANTONIO EDUARDO B. NACHURA Associate Justice |
TERESITA J. LEONARDO-DE CASTRO Associate Justice |
ARTURO D. BRION Associate Justice |
DIOSDADO M. PERALTA Associate Justice |
LUCAS P. BERSAMIN Associate Justice |
MARIANO C. DEL CASTILLO Associate Justice |
ROBERTO A. ABAD Associate Justice |
MARTIN S. VILLARAMA, JR. Associate Justice |
JOSE PORTUGAL PEREZ Associate Justice |
JOSE CATRAL MENDOZA
Associate Justice
Associate Justice
C E R T I F I C A T I O N
Pursuant to Section 13, Article VIII of the
Constitution, I certify that the conclusions in the above Decision had
been reached in consultation before the case was assigned to the writer
of the opinion of the Court.
RENATO C. CORONAChief Justice
Footnotes
2
Penned by Associate Justice Amelita G. Tolentino, with Associate
Justices Portia Aliño-Hormachuelos and Arcangelita Romilla-Lontok
concurring, rollo at 33-48.
3 Rollo at 51-55.4 Petitioners’ Answer, rollo at 56-59.
5 Sections 85-87, Ordaining and Instituting a Government Auditing Code of the Philippines (1978).
6 Rollo at 60-64.7G.R. Nos. 151373-74, November 17, 2005, 475 SCRA 218.
8 Rollo at 47.
9 G.R. No. 158253, March 2, 2007, 517 SCRA 255.
10Supreme Court Resolution En Banc, G.R. No. 84202, November 22, 1988, cited in Eslao v. COA, 195 SCRA 730.
11 G.R. No. 89745, April 8, 1991, 195 SCRA 730.12 G.R. No. 95938, August 16, 1991, 200 SCRA 705.
13 G.R. 131544, March 16, 2001, 354 SCRA 566.
14 Supra at note 7.
15 DOH v. C.V. Canchela Associates, Architects, G.R. Nos. 151373-74, November 17, 2005, 475 SCRA 218.
16 G.R. No. L-31635, August 31, 1971, 40 SCRA 464.17 G.R. No. 186192, August 25, 2010.
18 G.R. No. 131544, March 16, 2001, 354 SCRA 566.
No comments:
Post a Comment